Sprint Capacity Calculation

Definitions (variables)

Formulas

PlanningHours = Pd × H × Sp
DevHours     = (Dd + B) × H × Nd
TestingHours = Td × H × Nt
ReleaseHours = Rd × H × Nr
TotalHours   = PlanningHours + DevHours + TestingHours + ReleaseHours
    

Numeric Iterations

Common intermediate values:
H = 5, Nd = 5, Nt = 2, Sp = 2, Nr = 1

  1. PlanningHours
    2 × 5 × 2 = 20 hours
  2. TestingHours
    10 × 5 × 2 = 100 hours
  3. ReleaseHours
    3 × 5 × 1 = 15 hours

Case A — Minimum bug-fix (B = 2)
DevHours = (10 + 2) × 5 × 5 = 12 × 25 = 300 hours
TotalHours = 20 + 300 + 100 + 15 = 435 hours

Case B — Maximum bug-fix (B = 5)
DevHours = (10 + 5) × 5 × 5 = 15 × 25 = 375 hours
TotalHours = 20 + 375 + 100 + 15 = 510 hours